Prop R Timeline

  • This project timeline for the Prop R 2024 no-tax-rate-increase bond issue is a living webpage that will be updated in real-time and is subject to change. Updated June 2024.

    Concord Elementary School

    • Fall 2024: Safety upgrades

    Crestwood Elementary School - CMAR: BSI Architect: Perkins & Will

    • June 2024: Excavation begins
    • July 2024: Project construction begins on FEMA gym
    • Dec. 2024: Remodel of cafeteria/gymnasium
    • May 2025: Completion of FEMA gym
    • June 2025: Remodel of existing building
    • Aug. 2025: substantial completion remodel

    Dressel Elementary School

    • Fall 2024: Safety upgrades

    Kennerly Elementary School - CMAR: BSI Architect: BRS

    • May 2024: Schematic design
    • Aug. 2024: Design development
    • Winter 2024: Project bidding
    • Spring 2025: Project construction begins on FEMA gym
    • Dec. 2025: Project construction begins on remodel
    • Spring 2026: Project substantial completion on FEMA gym
    • Aug. 2026: Project substantial completion on remodel

    Long Elementary School - CMAR: BSI Architect: BRS

    • May 2024: Schematic design
    • Aug. 2024: Design development
    • Winter 2024: Project bidding
    • Spring 2025: Project construction begins on FEMA gym
    • Dec. 2025: Project construction begins on remodel
    • Spring 2026: Project substantial completion on FEMA gym
    • Aug. 2026: Project substantial completion on remodel

    Sappington Elementary School - Architect: Arch Images

    • Fall 2025: Schematic design
    • June 2026: Project construction begins
    • Aug. 2026: Project substantial completion

    Sperreng Middle School - CMAR: Holland Architect: Arch Images

    • Sept. 2024: Schematic design
    • Oct. 2024: Design development
    • Spring 2025: Project bidding
    • June 2025: Project construction begins
    • Aug. 2026: Project completion

    Truman Middle School - CMAR: BSI Architect: Perkins & Will

    • July 2024: Schematic design
    • Oct. 2024: Design development
    • Oct. 2024: Project bidding 1
    • Jan. 2025: Project bidding 1 construction begins
    • May 2025: Project bidding 1 substantial completion
    • Feb. 2025: Project bidding 2
    • June 2025: Project bidding 2 construction begins
    • Jan. 2027: Project bidding 2 substantial completion

    Lindbergh High School

    • Fall 2024: Natatorium Pool Mechanical Updates

    Lindbergh ECE

    Lindbergh Farmers Club - CMAR: BSI Architect: Perkins & Will

    • Aug. 2024: Schematic design
    • Sept. 2024: Design development
    • Jan. 2026: Project construction begins
    • Jan. 2027: Project substantial completion

    Support Services Center - Design, Bid, Build Project Architect: Arch Images

    • Aug. 2024: Schematic design
    • Sept. 2024: Design development
    • Oct. 2024: Project bidding
    • Jan. 2025: Project construction begins
    • June 2025: Project substantial completion